A permit needed for other approvals is holding up construction of Consolidated Water’s US$204 million desalination project in Hawaii.
The Cayman Islands-based company needs an archaeological permit before it can submit some of the other applications required for the Kalaeloa seawater desalination facility.
Chief executive officer Rick McTaggart disclosed the link during the question-and-answer session of Consolidated Water’s second-quarter earnings call on 11 August.
The company had previously said in July that it could not set a construction start date because of delays outside its and the Honolulu Board of Water Supply’s control.
“It’s definitely not the last one we need, but we have to have that as a prerequisite for some other permits,” McTaggart said.
The company is now looking at whether other applications can move ahead while the archaeological approval remains outstanding.
“We’re discussing ways to proceed with the applications on some of the other permits we need with the blessing of the archaeological regulator,” he said.
Consolidated Water is also examining ways to limit the effect of the delay on the construction schedule.
“We’re looking at ways to speed up the process without suffering further delays because of this linchpin permit delay,” McTaggart said.
The company said it remains “cautiously optimistic” that construction can start before the end of 2026.
The Honolulu Board of Water Supply issued a limited notice to proceed in July. This allows Consolidated Water to begin procuring about US$6 million of long-lead materials and equipment before all required permits are in place.
McTaggart said the early procurement is intended to reduce scheduling pressure once the remaining approvals are secured.
“The limited notice to proceed with the procurement of long lead equipment should help reduce potential scheduling pressure and allow the project to move forward more efficiently once the required permits are in place,” he said.
The company has also increased its communications and information exchanges with Hawaii’s regulatory authorities.
“The recent uptick in communications and information exchanges with key regulatory authorities in Hawaii supports our cautious optimism,” McTaggart said.
The Kalaeloa facility is designed to produce 1.7 million gallons of potable water per day.
Consolidated Water has been contracted to design, build, operate and maintain the facility under a 20-year operating term with potential extensions.
McTaggart said the project could become a significant contributor to the company’s future revenue and earnings once construction begins and the facility enters operation.
Consolidated Water had previously disclosed the wider permitting delays but had not detailed that the archaeological approval was a prerequisite for some other permits.