Moody’s: AI data centre boom masks growing power and delivery risks 

A completed artificial intelligence data centre is not necessarily a cash-generating asset, according to new research from Moody’s Analytics.

The study examines how the explosive growth of AI infrastructure is creating a category of credit risk that traditional financing frameworks may be poorly equipped to assess.

The report was authored by Hanna Sundqvist, head of private credit, Europe, and David Hamilton, head of asset management research at Moody’s Analytics.

It argues that the distinction between announced capacity and physically delivered, operational infrastructure is becoming one of the defining credit questions in private markets.

“A project can be structurally complete yet commercially immature. It can be energised but only partially operational,” the report states.

“It can possess contracted demand but still face delays associated with grid interconnection, staged commissioning, or deployment sequencing.”

The scale of the AI infrastructure build-out gives that warning considerable weight.

Moody’s Ratings estimates that capital investment by six major US hyperscalers, including Amazon, Microsoft, Alphabet, Meta, Oracle and CoreWeave, could approach US$785 billion in 2026.

That capital is flowing increasingly through private credit channels, including infrastructure debt, project finance structures, and institutional co-lending arrangements, rather than solely through traditional bank lending.

The research identifies four post-financing stages that are most relevant to credit analysis: physical delivery, energisation, commissioning and tenant deployment.

A facility can be physically delivered but not yet energised; energised but not commissioned; commissioned but only partially used.

For lenders, the economically relevant milestone is stable, contracted utilisation, not the completion of bricks and mortar.

Financing structures are being underwritten against assumptions tied to later operational stages, the paper argues, while the risks most likely to disrupt those assumptions are concentrated in earlier ones.

Power availability is emerging as a particularly acute constraint.

The International Energy Agency has projected global data centre electricity consumption rising from 485 TWh in 2025 to about 950 TWh in 2030, a trajectory that could represent one of the fastest expansions in industrial electricity demand on record.

Grid access delays, transmission bottlenecks, and the need for co-located on-site generation are introducing variables that sit largely outside a developer’s direct control and which existing credit models may not adequately capture.

To assess how construction progress aligns with announced timelines, the research draws on satellite-based geospatial monitoring data from Kayrros across three anonymised case studies spanning phased multi-gigawatt campuses.

Moody’s is careful to note that observable divergence does not automatically imply credit impairment.

Many delays reflect intentional phasing, fixed-price construction contracts that transfer risk to contractors, or lease structures under which tenants absorb cost overruns.

Satellite imagery cannot observe utilisation rates, contracted capacity, power draw, or cash flow generation, and geospatial data represents one input into analysis rather than a definitive statement of project status.

The issue is particularly relevant for funds domiciled in jurisdictions such as the Cayman Islands, which serves as the legal home for a significant share of the private credit and infrastructure debt vehicles financing AI development globally.

For fund managers and institutional lenders operating through Cayman structures, the study’s findings bear directly on how operational risk should be monitored and disclosed within financing documentation.

Delays in energisation or commissioning may affect debt service coverage ratios, stabilisation assumptions, borrowing base calculations, covenant headroom, refinancing risk, and projected residual values, even where near-term default risk remains low given the investment-grade credit profiles of hyperscaler tenants.

The research also flags a structural concern beyond the immediate financing cycle. “The insurance market faces a structural parallel,” the authors write.

“The growing divergence between replacement value and economic value in compute-intensive assets may be introducing risk characteristics that existing actuarial frameworks and policy structures may not yet fully capture.”

Looking ahead, the research indicates that the pressure on credit monitoring frameworks will only intensify as deals grow larger and more complex.

“As AI infrastructure financing scales further into private markets, larger, more levered, and more distributed across interconnected capital structures, the informational gap between announced capacity and observable operational progression may widen,” it concludes.

That is unless independent engineers or technical advisors are providing regular progress reports on construction, energisation and operational milestones.

RELATED ARTICLES

Most Popular

Reset password

Enter your email address and we will send you a link to change your password.

Get started with your account

to save your favourite homes and more

Sign up with email

Get started with your account

to save your favourite homes and more

By clicking the «SIGN UP» button you agree to the Terms of Use and Privacy Policy

Create an agent account

Manage your listings, profile and more

By clicking the «SIGN UP» button you agree to the Terms of Use and Privacy Policy

Create an agent account

Manage your listings, profile and more

Sign up with email