The Central Planning Authority (CPA) has approved the demolition of a fuel storage tank and the installation of a new 1,022,211-gallon tank at the Rubis Cayman Islands depot on South Church Street in George Town.
It follows the approval of a $1.9m application from Rubis in January to demolish a tank and install a new one measuring 717,827 gallons.
According to minutes from the 16 September meeting published on 1 October, the new CI$3 million application was approved with no objections and two conditions.
The first, as directed by the National Conservation Council, is that all construction materials and debris must be stockpiled landward of the existing retaining wall.
The aim is to prevent material from entering the Marine Protected Area as the site sits adjacent to the George Town South Marine Reserve.
The second, is that unless specifically authorised otherwise in writing by the Central Planning Authority, the development must be carried out strictly in accordance with the approved plans.
In a 2 July review, the Department of Environment flagged the “potential for contamination of the marine environment from the site,”
It said this could come “either operationally or via spills/leaks, due to the storage of large volumes of hydrocarbons and petrochemicals”.
The department added that operational risks were most appropriately addressed by OfReg and the Water Authority, and that its own concern was environmental impacts during construction.
It also said the operation should have a disaster risk management plan and a contingency plan for leaks or spills.
Other agencies set their own requirements in the planning document.
OfReg listed six hold points – soil under the tank at the end of demolition, vacuum testing of the bottom plates, hydrostatic pressure testing, cathodic protection commissioning, holiday testing, and a full set of quality control and assurance reports from independent third-party inspectors before the first tanker receipt.
The Water Authority requires an inspection of the fill material below the tank base after demolition “to verify that no fuel spills have occurred”.
Rubis faced regulatory action over the Jackson Point terminal due to diesel released from one of the terminal’s bulk tanks in November 2019.
OfReg charged Rubis with breaching section 12 of the Dangerous Substances Act, which requires operators of regulated premises to take all reasonable precautions to prevent a release or spillage.
CPA member Peter Campbell declared a conflict and left the room for the item.