Consolidated Water Co is moving ahead with early procurement for its seawater desalination project in Oʻahu, Hawaii.
The Cayman Islands-headquartered water treatment company said it has received a limited notice to proceed from the Honolulu Board of Water Supply.
This allows it to begin purchasing long-lead equipment for the seawater reverse osmosis desalination facility in the community of Kalaeloa.
The notice releases about US$6m in project funding to procure equipment needed for the plant, which is designed to produce 1.7 million gallons of potable water a day.
Construction has not yet started because of permitting delays that both Consolidated Water and the Board of Water Supply said are outside their control.
The company said the early procurement approval is intended to reduce the impact of those delays and help position the project for completion as soon as practicable.
Under its contract, Consolidated Water will design, build, operate and maintain the desalination plant.
After commissioning, the company will operate the facility for 20 years, with two additional five-year extension options at the client’s discretion.
Chief executive officer Rick McTaggart said in a press release the Hawaii development marks progress for both the company’s project operations.
“The limited notice to proceed reflects our Hawaii client’s continued commitment to advancing the Kalaeloa desalination facility while we manage permitting matters that are outside the control of both parties,” he said.
“Procuring long-lead equipment at this stage should help reduce potential scheduling pressure and enable the project to move forward more efficiently.”
Florida water treatment
In a separate development, the company said it has received purchase orders worth about $10.1m from a municipality on Florida’s east coast for nanofiltration membrane water treatment equipment and horizontal cartridge filters.
Consolidated Water said these are the largest municipal orders it has received for membrane-based water treatment equipment and for its horizontal cartridge filter product line.
Delivery of the equipment is scheduled for November 2027.
McTaggart said: “The $10.1m in Florida purchase orders further demonstrate the strength and breadth of our manufacturing capabilities.
“Securing our largest municipal membrane equipment order and our largest horizontal cartridge filter order to date represents a significant achievement for this business.”